Abstract
Faced with the uncertainty of wind and photovoltaic power output and
load fluctuation caused by the increase of new energy penetration in
active distribution network, the demand for operational flexibility and
the construction demand for flexible resources of distribution network
are gradually increasing. The flexible operation of active distribution
network can be realized by coordinated planning of the soft open point
integrated with energy storage system (ESOP) and flexible resources.
Firstly, the flexibility resource adjustability evaluation and margin
indicators are proposed for the response model of typical flexibility
resources. Secondly, a two-stage distributionally robust coordinated
planning model considering the coordination planning scheme of
distributed generation, flexibility resource and ESOP as well as the
comprehensive norm uncertainty of wind power and photovoltaic outputs
multi-operation scenarios is established with the distribution network
construction cost, annual operation cost and annual power sales revenue
as the objective functions meanwhile the investment and flexibility
resource operation as constraints. Finally, the column constraint
generation algorithm is used to solve the problem, and the effectiveness
of the proposed model is verified by the modified IEEE33 node system.